Lahore Smart City Development Update

A soil test of the work site, carried out after the middle of the year in 2020, served as the first step in the planning and design of Lahore Smart City.

Soon after the NOC was approved, the machinery was put on the site. This suggests that the project will advance more quickly and continuously.

Current Area of Development

With roads leading at the project's entrance, the development work for society has begun. The roads that are currently being built are shown by the pink-colored roadways in the map's highlighted region.

Construction of Smart Villas

Recently, construction on the Smart Villas in Lahore Smart City's sector A began. Earthwork and excavation are now being done.

For 1 Kanal and 10 Marla Georgian-style villas in sector A, the brickwork has started. The mental beam are being put in place, and brick walls have already been built.

Construction of Roads & Lanes

For the purpose of advancing the building of Main Boulevard B-1 and main roads C-1, F-1, F-2, F-3, F'-1, G-1, G-2, and G-3, the soil has been leveled and subgrade layers have also been created.

Outdoor lighting poles are also being put along B-1 & C-1 roads, and the curb stones have been fastened at B-1 Road. Additionally, road sleeves for type G and type M highways are being built beside and across C-1 Road. Manholes and road drains are currently being built.

Lahore Smart City
Sector A and B's road and lane building has also begun and is a good underpass. Additionally, repairs to the edge stones and plantations along the roadways are ongoing.

Building of Streets and Driveways

Sectors A and B now have driveways, pathways, and roadways under development.

After leveling the ground for the streets, work has begun on the excavation and building of the street drains. Sector A has completed the construction of Streets 1, 2, 3, and 4. In all areas, driveways and footpaths are being built quickly as well. Additionally, roadway planting is ongoing.

Building a Boundary Wall and Sewage

Sector B's border wall is currently being built.

In sectors A and B, sewage pipeline construction is taking place.

Building of Site Offices

To entice site visitors and investors, Lahore Smart City is building a large site office. A sales and marketing office is also getting its concrete base poured.

Plantation of trees and horticulture

To ensure that the plants and trees are ready on time for horticulture work, tree planting has already begun at the on-site nursery in addition to the roads leading.

Every housing development includes horticulture, plantations, and green belts as a natural aspect of life. Lively green vegetation along the roadside gives the new society a warm and welcoming appearance and symbolizes the excellence of any residential project's construction.

Lahore Smart City

Public Facilities

All the fundamental conveniences required for a respectable community are provided by the infrastructure of the society. Additionally, faster development is taking place to give future homeowners access to these facilities as soon as possible.

Building a septic tank with a water tank

Sector A's above-water reservoir has had construction finished. Sector B is currently constructing an overhead water tank.

Electricity

Power Thanks to the installation of 200 KVA WAPDA TrAnsformer, the development site's office and other facilities will have electricity.

Parks

Work on the neighborhood park in sector A has started.

The planting will shortly begin when the edge stone repair is finished.

Mosques

The construction of mosques in sectors A & B is well underway.

Lahore Smart City

Institutes of Higher Learning

Sector B of Lahore Smart City hosted the groundbreaking ceremony for the Girls & Boys College. The work on the development is almost finished.

Overseas Block

As the name implies, the overseas block is just for Pakistanis who reside outside of Pakistan. To be qualified to purchase a plot with an overseas block, the people would need to show documentation of their residency in the foreign nation. However, locals can also purchase the documents in the foreign block used.

Residential plots in this block are available in sizes of 5, 10, and 20 Marla. After that, the 7 marlas or 12 marla plots were also made available, and reservations are now being taken for these recently published plots.

Watch this space for updates on the Overseas block's progress.

Executive Block

For local Pakistanis, the executive block provides housing and investment prospects. This block, like the other blocks in Lahore Smart City, offers top-notch features and services to create a beautiful environment for society's future citizens.

Residential plots of 5, 7, 10, 12, and 20 Marla are also available on this block. These plots are available for purchase in installments and need a 20% down payment.

Keep checking back for updates on the Executive block's construction at Lahore Smart City. Installments

Is Lahore Smart City a good investment?

Investors always look for the answers to these questions before launching a project in order to make a well-informed choice. One of the few projects that earned popularity even before its debut and maintained it thereafter is Lahore Smart City. Read our blog post Lahore Smart City - Payment Plan and Latest Market Prices if you've been wondering why this is the case.

2.66 and 6 marla business plots in Lahore Smart City are now available for booking with a 10% down payment. The group introduced 4 and 8 marla commercial plots last year. View the full schedule of payments for commercial plots.

Comments

Popular posts from this blog

The Future of Smart Living Predictions for Lahore Smart City

5 Reasons To Invest In Capital Smart City | Why To Invest?, All Details

How Capital Smart City Can Make a Difference in Pakistan’s Future